Information
About Storm Drainage
Overview
| Cost | Timeline
| Process | Benefits
| Concerns
Overview
As a barrier island, with relatively low average
land heights above sea level, Palm Beach is particularly susceptible
to storm and rainfall events including tropical storms, hurricanes
and related flooding. The Town experienced a devastating flood over
Thanksgiving 2000, and after much planning and public discussion,
the Town embarked on a Storm Drainage Plan in 2002. However, due
to recent property tax reforms and a subsequent 5 percent cut in
the Town’s tax rate, the “Pay-As-You-Go” program
can no longer be supported on a cash basis out of the Town’s
capital improvement fund.
The Town seeks $13 million in general obligation
bonds to complete the improvements outlined in the Storm Drainage
Plan. A referendum date of December 18, 2007 has been set for voters
to decide whether to assume the debt in order to complete the Storm
Drainage Plan.
Currently, the ground floors of many homes in Palm
Beach are vulnerable to flooding if another large storm comes through
the area. Flooding could cause extensive property damage, and could
prohibit access to roads for emergency management vehicles. The
Town Council wants to continue the Storm Drainage Plan to minimize
flooding and increase storm protection in the area. The program
cannot be completed in a reasonable amount of time, while complying
with state property tax reduction mandates, without public approval
of the proposed funding.
The first five years of the program allowed the
Town to complete construction of stormwater drainage sites on Everglade
Avenue, North Lake Way, Tangier Avenue and Country Club Road.
For a map of where drainage improvements already have been completed
and where they remain to be implemented, click here.
However, additional work is required to seamlessly
link the entire North End of the town and to reduce the threat of
flooding to residents and property. If funding is approved, work
is scheduled for May 2008. Work would take place during the off-season
between May and November for the next six years in order to minimize
the impact of construction on traffic and residents. Construction
is expected to be complete by the end of 2013.
The drainage program involves constructing a series
of stormwater pump stations and upgrading stormwater collection
systems with new larger diameter pipes, manholes and drain inlets.
The system is designed to minimize the number of houses that would
be flooded due to stormwater and rainfall events or a tropical storm
or hurricane.
For a list of scheduled work sites, click here.
Cost
The preliminary estimated cost to complete the Storm
Drainage Plan is $13 million. The cost would be paid by taxpayers
through 30-year general obligation bonds with annual payments (Schedule
A tax deductible, if applicable) based on the taxable value of each
property.
As of the fiscal year ending September 30, 2007,
the capital improvement fund balance available for drainage was
$4.4 million. This funding is earmarked for drainage improvements
identified in the Storm Drainage Plan, but the additional funding
being requested for voter approval is needed to complete the Plan.
The funding proposed in the general obligation bond referendum is
$13 million. Based on the approval of a $13 million general obligation
bond, the drainage plan would have an annual cost to residents of
$66 per $1 million of taxable property value. That breaks down to
an estimated daily cost of approximately $0.18 per $1 million of
taxable property value.
The Storm Drainage Plan was originally approved
by the Town Council in 2002 and funded by “Pay-As-You-Go”
monies from the capital improvement funds, which were funded in
large part with property taxes. Due to recent property tax reforms
and a subsequent state mandated 5 percent cut in the Town’s
tax rate, there is no longer enough revenue in the Town’s
capital improvement fund to complete the drainage project and meet
the State’s new budget reduction requirements. It is estimated
this bond will allow the Town to complete the drainage work outlined
in the plan and that no additional funding will be required for
this particular construction project.
Timeline
If funding is approved, the project is scheduled
for May 2008, with the goal of completion by November 2013. Completing
the program is estimated to require a maximum of six off-season
construction periods to complete.
Back to Top
Process
The process of improving stormwater drainage involves
constructing a series of stormwater pump stations and collection
systems with manholes, larger diameter pipes and drain inlets. These
improvements move excess water off of and away from the streets,
before it can back up and flood buildings.
During construction the road right-of-way would
be closed, where necessary, to allow work crews to install new drain
inlets and upgrade the existing stormwater collection system. The
system will be designed to meet new drainage service guidelines
adopted by the Town Council, and to minimize the number of houses
that would be flooded due to storm and rainfall events including
tropical storms or hurricanes.
The work would be done in pre-determined phases,
each including the installation of pipes in the street. Excavation
equipment would be used to remove portions of the road and install
larger diameter pipes. Pump stations would be upgraded to handle
increased volumes of stormwater. The pipes would typically discharge
water to the Intracoastal Waterway, eventually funneling the water
to the ocean. Once the pipes are installed in a particular phase,
that section of road would be patched or repaved for the full width,
depending on the extent of excavation.
Although the streets may still collect water in
the event of a major storm, after completion of the project fewer
homes should take on water. Specifically, the portion of the system
in question would provide protection for homes at a first floor
elevation of 5 feet and above in Basin D-4, Basin D-8, and Basin
D-10. It would also provide first floor protection for homes at
elevation 5 feet 5 inches in Basin D-2 and 6 inches in Basin D-9.
For a map of the locations where protection will be provided, click
here.
If Palm Beach voters approve the requested funding,
construction is scheduled in Basin D-8 and Basin D-9 first.
For a list of scheduled work sites, click here.
Back to Top
Benefits
Improving the Town’s stormwater drainage system
provides two primary benefits to our community: preventing property
damage caused by storm-related flooding and preserving access to
roads for emergency vehicles.
The primary benefit to residents is the reduced
risk of flood waters damaging personal property, such as homes,
landscaping, furniture and belongings inside of homes, and other
items such as vehicles that may be permanently damaged by flood
waters.
In addition, the improved drainage will facilitate
access for emergency vehicles in the aftermath of a severe storm
or hurricane. Without completion of the Storm Drainage Plan, heavy
flooding on the town’s roads may prevent emergency vehicles
from reaching homes and businesses where residents need assistance.
Back
to Top
Concerns
The primary concerns residents may have with the
stormwater drainage improvement program are cost,
method of payment, proximity and
construction.
Cost
In order to complete the Storm Drainage Plan, the Town of Palm Beach
requires $13 million. This estimate equals an annual cost to residents
of $66 per $1 million of taxable property value, or an estimated
daily cost of approximately $0.18 per $1 million of taxable property
value.
Method of Payment
If the project funding is approved in the December 18, 2007 referendum,
taxpayers will assume the debt of $13 million in general obligation
bonds with annual payments (Schedule A, tax deductible, if available)
based on the taxable value of each property. It has been determined
by the Town Council that bonds are required to fund the completion
of drainage work, as the Town’s reduced post-property tax
reform tax rate can no longer sustain “Pay-As-You-Go”
funding for drainage improvements of this extent. Without issuance
of general obligation bonds to fund drainage improvements, the Town
will be unable to complete this project in a reasonable amount of
time, while complying with state property tax mandates.
Proximity
Residents not residing in the proposed improvement
area may question taking on debt to fund drainage improvements primarily
slated for the North End. There are two considerations to that concern:
| |
1) |
North End residents
have already contributed to the storm protection drainage improvements
made elsewhere in Town during the first five years of the Storm
Protection Plan and for the storm protection benefits received
from the beach renourishment projects constructed in recent
years. That is because the Storm Protection Plan drainage improvements
were funded by capital improvement funds, which came from property
taxes collected from the entire Town as were the revenues that
were pledged to retire the debt on the 2000 Comprehensive Coastal
Management Plan beach nourishment projects that have been completed.
It would not be fair to segregate funds now for completing Storm
Protection Plan improvements in the North End.
|
| |
2) |
Drainage is a town-wide issue.
Any damage to public property that may occur from a lack of
drainage will be paid for by the entire town. |
Construction
The project would involve road excavations,
which could impact local traffic in the form of road closures and
re-routing. Construction would take place during the off-season
period of May 1 through November 30, when the local population decreases,
in order to minimize the impact on residents. Construction is expected
to be complete by November 2013.
Back to Top
For more specific information regarding the undergrounding
costs, timing and process, please visit the Frequently
Asked Questions page
|