Information
About Undergrounding
Overview
| Cost | Timeline
| Process | Benefits
| Concerns
Overview
The undergrounding process involves removing the
electric, telephone and cable television wires that are customarily
carried on above ground poles and burying them in underground conduits,
vaults or trenches. Undergrounding is typically preferred
to overhead system improvements, as the added benefits include fewer
outages and associated repairs,
improved aesthetics to resident and town property, improved
health and safety of residents, and less economic impact due to
outages.
With 87 percent of residents experiencing outages
for more than one week after the latest hurricanes, the pending
Florida Public Service Commission (PSC) mandates to increase reliability
and the potential benefits provided by underground electric utilities,
the Town Council believes that conversion from overhead to underground
utilities warrants citizen consideration.
Burying Palm Beach’s electric, telephone
and cable television utilities would require an additional annual
tax payment for residents and an extended implementation timeline,
so the Town believes residents should be given the opportunity
to decide whether or not to engage in this type of project. A referendum is anticipated to be held in late 2008 or in early 2009 in which Town residents will decide whether or not the project should move forward.
Cost
The cost of an undergrounding project would be paid
by taxpayers through 30-year general obligation bonds with annual
payments (Schedule A tax deductible, if applicable) based on the
taxable value of one’s property.
The preliminary estimated cost of the project would be $89,450,000. This figure includes a 25 percent credit from Florida Power & Light (FPL), approved by the PSC. Based on a market interest rate of 4.67 percent the updated cost estimate would equate to an annual cost to property owners of $212 per $1 million in taxable property value for debt service years 1-5; $454 per $1 million in taxable property value for debt service years 6-30; and, $242 per $1 million in taxable property value for debt service years 31-35. That means an estimated daily cost of approximately $0.58 for debt service years 1-5; $1.24 for debt service years 6-30; and, $0.66 for debt service years 31-35, all based on cost per $1 million in taxable property value. A final, official estimate of the project cost will be provided with sufficient time for residents to review before voting and in some cases, binding cost estimates from the affected utilities. The PSC determined that a 25 percent credit shall be given in recognition of avoided storm restoration costs realized by FPL by virtue of underground facilities and will be instituted for a two-year trial period for local government underground conversion projects. This approved credit tariff, called the GAF tariff, is estimated to save the Town's residents $6.18 million or more in electric utility underground conversion costs. The Town's project, if approved by voters, would receive this credit for the duration of the project, as long as a master contract is signed with FPL prior to October 4, 2008. The Town and other interested municipalities anticipate formally seeking a time extension to this PSC tariff or requesting PSC action that will make the credit tariff permanent. In addition, another credit tariff is anticipated to be considered by the PSC in early 2008 that will be representative of the avoided operations and maintenance costs avoided by FPL by virtue of the benefits of installing underground electrical facilities. One can anticipate the Town working diligently to secure these additional underground construction cost savings in 2008.
Timeline
A referendum is anticipated to be held in late 2008 or in early 2009 in which Town residents will decide whether or not the project should move forward.
Once the referendum is held, and if the project
is approved, work will begin as soon as possible. The impacts
to individual streets and private property are expected to be
minimal, as each phase of the conversion, which will include
multiple streets, is expected to last approximately one year. The
overall process to convert the town will take an extended period
of time because of the magnitude of the project (current estimates
gauge approximately 10 years as the worst case scenario). The
determination of where phases will begin and end will be made
at a later date, once the Town's engineers and consultants have
had the opportunity to thoroughly analyze each utility's infrastructure
layout.
Back to Top
Process
If approved by voters, the undergrounding project would include a 100 percent conversion of the town's utilities including FPL, BellSouth and Comcast. Almost 40 miles of utility grid would be buried, with 100 percent of current poles being eliminated.
Utility wires will be buried throughout the town
primarily within the road right-of-way using a geographically
phased approach. Each phase of the process will consist of several
steps, with the first to establish and obtain routes and easements.
Then conduit will be installed by one contractor using a combination
of horizontal directional drilling (HDD) and trenching. HDD
is anticipated to be the primary means, as it is less invasive
and results in less disruption to traffic and roadways. Trenching
will be done with a back hoe, Bobcat or Ditch Witch in some
areas, as it is a less costly process. Once the conduit is installed,
the utility companies will install ground-based equipment such
as transformers, switch cabinets and decorative streetlights.
Next, the utilities will run their lines through the conduit.
Those lines will then be connected to homes and equipment and
the new underground system will be activated, along with the
new street lights. Finally, the overhead system will be deactivated
and removed.
Dark green metal cabinets would be strategically placed to accommodate the transformers and switch cabinets that are necessary to the electrical system. Underground switch cabinets are being contemplated and the cost for such is included in the cost estimate. This should eliminate any remaining aesthetic concerns for such facilities wherever the Town is able to incorporate such into the construction plan. They are expected to reside in the road right-of-way to avoid personal property disruption, except in very rare cases where this is not possible..
Back to Top
Benefits
A recent survey showed that residents of the Town
of Palm Beach believe underground utilities will benefit them in
several ways. Those benefits include:
- Improving the aesthetic value of homes and of the town as a whole.
- Affording more reliable power service.
- Reducing outages and service loss during storms and damage from
hurricane winds.
- Improved safety for residents.
Back
to Top
Concerns
The survey showed that the primary concern among
town residents was the cost of the project and the taxes required
to provide funding to retire the project debt. Another major concern
the residents expressed was the impact of the construction on traffic
and the duration of that impact. All concerns are being carefully
considered. When further information is available, it will be provided
both on this Web site and directly to residents.
Back to Top
For more specific information regarding the undergrounding
costs, timing and process, please visit the Frequently
Asked Questions page
|